Recessed entry of a modern home with charcoal cedar siding, light stucco, black-framed glazing, and a damp concrete approach beside a vine maple and ferns.

NW Sammamish Road Closure in Issaquah: Detours and What Stays Open

October 8, 2026

At 7 a.m. Monday, October 5, the Washington State Department of Transportation fully closes NW Sammamish Road just west of Lake Sammamish State Park. The closure lasts six weeks, and drivers will detour via West Lake Sammamish Parkway Southeast and I-90. Those six weeks are utility work. Crews are moving power and other lines out of the way so a new bridge can go in over Schneider Creek, a small stream near the west edge of the park. The bridge work brings a second full closure of the same road in early 2027, and the City expects that one to last four months.

The reason for all of this is a fish problem. The schedule puts the first closure in October, the month salmon spawning draws crowds to the Issaquah Salmon Hatchery a few miles upstream.

A 33 Percent Creek

WSDOT's project page says Schneider Creek runs under I-90 at the west edge of Lake Sammamish State Park and is only 33 percent passable for fish. The creek carries coho, sockeye, steelhead, resident trout and sea-run cutthroat. WSDOT estimates that a larger structure would open nearly three-quarters of a mile of new habitat.

Schneider is one of three creeks in a single $204 million contract. The other two have worse barriers. WSDOT rates the culverts under I-90 at Lewis Creek near Lakemont Boulevard and at West Village Park Creek near Southeast 51st Street as completely impassable. Lewis Creek alone could gain more than 2.5 miles of habitat for Chinook, coho, sockeye, steelhead and cutthroat. Atkinson Construction holds the contract.

The urgency comes partly from a court order. WSDOT ties the work to its obligation under a 2013 U.S. District Court injunction to remove fish barriers under state highways:

"Opening habitat allows more salmon and steelhead at all life stages, including juveniles that aren't yet strong swimmers like adults, to access important spawning and rearing habitat, including areas that haven't been accessed in years."

Two Closures on One Road

The Schneider Creek bridge is why NW Sammamish Road closes twice. WSDOT's published timeline lays out the sequence:

  1. February 2026. Westbound I-90 construction began, with traffic shifted onto bypass lanes.
  2. October 5, 2026. NW Sammamish Road closes for six weeks of utility relocation west of the park.
  3. January 2027. NW Sammamish Road construction begins with a full closure.
  4. Spring 2027. NW Sammamish Road construction is complete, and eastbound I-90 traffic shifts to its own bypass.

The City describes the 2027 phase in plain terms. Contractor crews will remove the old culvert, then build a bridge and a new creek bed along NW Sammamish Road, using the same detour routes and local access as this fall. WSDOT's project page lists completion at all three creeks by December 2029.

The fall closure works as a preview, then. Six weeks from October 5 brings the road to mid-November. Whatever weekday route people settle on between now and then is likely the one they will use again for four months starting in January.

What the Detour Changes

The official notices are brief. Homes inside the closure keep local access, and everyone else is sent around on West Lake Sammamish Parkway Southeast and I-90. WSDOT and the City place the work "just west of Lake Sammamish State Park" but don't name cross streets for either end of the closure. Neither notice announces any bus reroutes or a walking and biking pass-through. Anyone who commutes by bike along this stretch should check with WSDOT before assuming the road is passable.

The City also warns of westbound I-90 traffic shifts near the 17th Avenue Northwest and Lakemont Boulevard interchanges, overnight lane reductions, and detours around closed ramps and surface streets. It gives no dates for those ramp closures. WSDOT Communications takes questions through Tom Pearce at 206-440-4696.

Most of the Gilman corridor is reached from the other direction anyway. Issaquah Commons, at 705 to 975 NW Gilman Blvd, gives its own driving directions from I-90 Exit 15 via 17th Avenue NW and Gilman Boulevard.

The Park Stays Open, Minus Its Own Closures

Washington State Parks posted a notice on October 2 saying Lake Sammamish State Park will remain open through the road closure. It warns of increased congestion getting into the park from early October to late November, and keeps the notice up through November 30. Day use and the watercraft launch both appear as open on the State Parks winter schedule.

Some parts of the park were already closed before WSDOT arrived, and the road closure doesn't change them:

  • Issaquah Creek bridge. Closed since a March 3 notice after erosion from high winter creek levels, with no repair timeframe. An October volunteer notice confirms it is still closed for safety.
  • Tibbetts Creek bridge. Closed under the same March notice, with no repair date posted.
  • Homestead Trail. Closed until further notice because of a washout.

Parking still requires a Discover Pass, which costs $10 for one day or $45 for a year.

A Fall Calendar That Still Works

Several events this fall involve the creeks and fish behind all this construction, and the organizers have kept them on the schedule.

At and around the park

  • Saturday, October 10. Mountains to Sound Greenway's annual tree-planting celebration, with an optional Issaquah Creek walk. Volunteers meet near 5150 220th Ave SE, and the work site is reached by stairs because the Issaquah Creek bridge is closed.
  • Saturday, October 17. A fall restoration volunteer session with Friends of Lake Sammamish State Park.
  • Sunday, October 18. Walk n Wag Harvest, the Friends group's free, leash-friendly walk.
  • Wednesday, November 4, 5:30 to 7:30 p.m. Lakeside Lectures: Kokanee, on the kokanee salmon native to Lake Sammamish, with UW professor Jeff Jensen and Dave Kyle of Trout Unlimited. Registration is open through the Friends group.

At the hatchery

The Issaquah Salmon Hatchery, built in 1936, raises Chinook and coho that come back through Lake Sammamish and up Issaquah Creek each fall. It is open daily and free, and spawning takes place on Tuesday and Wednesday mornings in October. So the salmon come up through the same lake that Schneider, Lewis and West Village Park creeks drain into.

Along the Exit 15 side

Pickering Barn, at 1730 10th Ave NW, has a full fall schedule:

  • Just Between Friends resale pop-up, October 8 through 11
  • BOO at the Barn, Saturday, October 24
  • Free clothing donation event, Monday, October 26
  • Free clothing shopping, Wednesday, October 28
  • Tots & Trees, Saturday, November 14

The Saturday Issaquah Farmers Market ended its season on September 26, so it's off the fall calendar.

Pier 88 Boiling Seafood & Bar lists its address as 1151 NW Sammamish Rd. The Issaquah Chamber held its ribbon cutting there on July 2. The official notices don't say whether that address falls inside the closure, so it's worth calling ahead before a weeknight dinner.

Rock and Roll Rink, at 5700 E Lake Sammamish Pkwy SE, is running a Columbus Day camp and an open skate on Monday, October 12.

Planning Around January

By WSDOT's own timeline, the six weeks starting Monday are the shorter of the two closures. The second one, in January 2027, runs about four months and uses the same detour and local-access arrangement. Its purpose is a bridge over Schneider Creek, replacing a culvert fish can only get through a third of the time. The City says more outreach will come before that phase starts, and WSDOT's project page has an email update list for anyone who wants notices before the next closure begins.

If you're thinking about how a two-phase road project near Lake Sammamish State Park might affect when you list a home or schedule showings over the next year, Craig Northwest Homes can go over the WSDOT timeline with you for your street. Get a free home consultation.

Work With Us